BATTERY STORAGE
INTEGRATION GUIDE

Protecting Solar Investments from the Cyprus Curtailment Crisis

2025 Edition

Published by LIGHTHIEF CYPRUS LTD

Official Tier-1 BESS Reseller

The Curtailment Crisis

CRITICAL MARKET ALERT:

Cyprus solar curtailment has surged from 0% (2021) to 45.8% (2025) based on actual operational park data. This represents nearly €1 million in annual lost revenue for a typical 5MW park.

Real Park Example - 5.01MW with Tracking:

YearProduction (MWh)Curtailment %Revenue Impact
202110,1460%€2.03M (full)
20229,8973.5%€1.98M (-€50k)
20238,86113.4%€1.78M (-€250k)
20247,43626.7%€1.49M (-€540k)
20255,59945.8%€1.06M (-€970k)

BESS Solution Overview

How Battery Storage Solves Curtailment:

  1. Capture: Store energy during curtailment periods instead of losing it
  2. Shift: Discharge during evening/night when demand is high
  3. Monetize: Sell at premium night tariff rates (20-30% higher)
  4. Protect: Future-proof against increasing curtailment

BESS Economics - Real Numbers

Investment:

Returns (5MW Park Example):

Sizing Methodology

Factors to Consider:

  1. Curtailment Profile: Historical and projected curtailment %
  2. Park Capacity: MW size of solar installation
  3. Cycles per Day: How many charge/discharge cycles
  4. Tariff Differential: Day vs night pricing spread

Recommended Sizing Options:

MWh per MWUse CaseRecovery Rate
0.5Minimal curtailment (<15%)30-40%
1.0Moderate curtailment (15-30%)40-50%
2.0High curtailment (30-45%)50-60%
2.5Very high curtailment (>45%)50-70%

Lighthief Cyprus BESS Services

As Official Tier-1 Reseller, we provide:

Local Service Advantage:

Unlike international suppliers, Lighthief Cyprus provides same-day emergency response from our Limassol headquarters. Critical for maximizing BESS uptime and ROI.

Case Studies

Case Study: 5MW Park ROI Comparison

MetricSolar OnlySolar + BESS
Total Investment€7,500,000€9,250,000
Annual Revenue€1,410,000€1,704,000
Annual Profit€1,272,000€1,541,000
Cash ROI13.3%13.6%
With 70% FinancingN/A (cap limit)20.2%

Implementation Timeline

BESS Retrofit: 14-22 weeks total

  1. Assessment & Design: 2-4 weeks
  2. Procurement & Permitting: 8-12 weeks
  3. Installation & Commissioning: 4-6 weeks