Engineering, Procurement & Construction for Solar Farms & Battery Energy Storage Systems in Cyprus

€0.61-0.73
PV EPC per Wp
8-13%
Equity IRR
2017
Founded
300+
Sunny Days / Year

1. About the Lighthief Group

1.1 Group Overview

Lighthief is a European clean energy group founded in 2017, operating across the solar lifecycle — from development and EPC construction to operations, monitoring, and end-of-life recycling. Our unique heritage gives us unmatched perspective on long-term asset performance and sustainability.

8+
Years of Experience
Cyprus
Headquarters — Limassol
Tier-1
Equipment Partnerships

1.2 Our Evolution

2017 — Foundation
Solar Panel Recycling Pioneers
Founded by Darius and Arkadius to address the growing need for sustainable solar panel end-of-life solutions. This heritage gives us unique lifecycle expertise that informs every project we deliver.
2019 — Expansion
Operations & Maintenance Services
Expanded into comprehensive O&M services for existing solar installations. Developed 24/7 monitoring capabilities, preventive maintenance programs, and performance optimization expertise.
2022 — Growth
BESS Integration Specialist
Became an official Tier-1 BESS reseller with partnerships with leading manufacturers. Pioneered battery storage integration for curtailment mitigation in the Cyprus market.
2024 — Full EPC
Complete EPC Contractor
Evolution into a full-service EPC contractor, offering end-to-end project delivery from design through commissioning. Cyprus-headquartered with international standards and supply chain.
2025 — Scale
Large-Scale Portfolio Deployment
Executing large-scale BESS portfolio across 47 Cyprus solar parks (863+ MWh). Proven delivery capability for utility-scale projects with confirmed Tier-1 equipment supply chain.

1.3 Lighthief Cyprus Ltd

DetailInformation
Company NameLighthief Cyprus Ltd
RegistrationHE 477423
Tax ID60187188Q
Address28 October Ave 249, Lophitis Business Center 1, Office 201, 3035 Limassol, Cyprus
SpecializationSolar EPC, BESS Integration, O&M Services, Asset Recycling
CertificationsETEK Certified Engineers, EU Battery Passport Compliant

2. EPC Services Overview

2.1 What We Deliver

Lighthief provides complete turnkey Engineering, Procurement & Construction (EPC) services for solar photovoltaic parks and Battery Energy Storage Systems (BESS) in Cyprus. Our integrated approach covers the entire project lifecycle:

1
Assessment & Design
2–4 weeks
Solar irradiation analysis, grid feasibility, optimized layout design, financial projections with realistic 8-13% IRR targets, and environmental impact assessment.
2
Engineering & Procurement
4–6 weeks
Complete electrical and structural engineering, Tier-1 equipment procurement with full supply chain management, grid connection design, and regulatory compliance.
3
Construction & Installation
8–16 weeks
Civil works and foundations, professional equipment installation by certified specialists, MV infrastructure, quality assurance protocols, and full safety compliance.
4
Commissioning & Handover
2–4 weeks
System testing and performance verification, grid connection certification, ETEK engineer sign-off, warranty documentation, and transition to O&M services.

2.2 The Lighthief Advantage

Why Lighthief EPC?

3. Solar PV EPC Pricing

3.1 Turnkey PV Pricing by Size

Complete turnkey solar PV EPC pricing, fully installed and commissioned:

Park Size (MWp) Total EPC Price Price per MWp Price per Wp
1 MWp €730,000 €730,000 €0.73
2 MWp €1,380,000 €690,000 €0.69
3 MWp €1,980,000 €660,000 €0.66
5 MWp €3,200,000 €640,000 €0.64
10 MWp €6,100,000 €610,000 €0.61
Economies of Scale: Larger projects benefit from significant unit cost reductions. A 10 MWp park costs €0.61/Wp compared to €0.73/Wp for 1 MWp — a 16% cost improvement.

3.2 What's Included in PV EPC

Included in EPC Price
  • Tier-1 solar modules (590W)
  • String inverters (Huawei)
  • Mounting structure & piling
  • DC & AC balance of system
  • MV station & transformer
  • Civil works, grading & fencing
  • Installation labor & machinery
  • Engineering, HSE & QA
  • Commissioning & certification
  • Performance warranties
  • Logistics & port handling
Client Pays Separately
  • RTB license (€350,000/MWp)
  • Off-site grid reinforcement
  • Land purchase or lease
  • Financing costs
  • VAT (19%)

4. BESS Pricing

4.1 Battery Energy Storage Systems

Lighthief provides complete turnkey BESS solutions using Tier-1 equipment, fully installed, commissioned, and grid-connected:

BESS Size (MWh) Price per MWh Total Price Equipment
4 MWh €168,500/MWh €674,000 Linyang ME / Kehua PCS
8 MWh €135,500/MWh €1,084,000 Linyang ME / Kehua PCS
10 MWh €124,100/MWh €1,241,000 Linyang ME / Kehua PCS
20 MWh ★ Most Popular €112,600/MWh €2,253,000 Linyang ME / Kehua PCS
40 MWh €109,800/MWh €4,392,000 Linyang ME / Kehua PCS
Volume Advantage: BESS pricing benefits significantly from scale — from €168,500/MWh at 4 MWh down to €109,800/MWh at 40 MWh (35% cost reduction).

4.2 BESS Technical Specifications

SpecificationValue
Battery ChemistryLFP (Lithium Iron Phosphate) — EVE 314Ah cells
ContainerLinyang ME 5.015 MWh integrated container
PCS / InverterKehua BCS1250K-C / BCS10000K-C-HUD
Round-Trip Efficiency86.32% AC-AC (full system incl. cabling)
PCS Efficiency≥99% max, ~98% at rated power
CoolingIntegrated liquid cooling system
Fire SuppressionIntegrated in container
BMS3-tier: BAMS / BCMU / BMU (Linyang integrated)
Grid FormingGrid forming capability included
EU Battery PassportCompliant
Warranty5 years manufacturer warranty
Design Life15+ years at 1 cycle per day

4.3 BESS Scope of Work

Included in BESS Price
  • Battery containers (EVE 314Ah LFP)
  • PCS / Inverters (Kehua)
  • MV Skid (Transformer + Switchgear)
  • RMU & Switchgear (Schneider)
  • BMS, Liquid Cooling, Fire Suppression
  • Surge Protection (SPDs)
  • Internal Earthing Grid
  • EMS / SCADA system
  • Import & customs duties
  • Civil works, concrete bases & cable laying
  • Drainage system
  • Installation & commissioning (4-6 weeks)
  • ETEK engineer certification
  • CERA license (€0.10/kWh)
  • EOL recycling (zero net cost)
Client Pays Separately
  • External Lightning Protection (DEHN — coordinated by Lighthief)
  • Site earthing enhancement (if needed)
  • EAC testing & connection fees
  • Communication equipment to TSO/EDC
  • VAT (19%)

5. Combined Solar + BESS Projects

5.1 Complete Park Pricing (PV + BESS)

Integrated pricing for combined solar and battery storage projects:

Configuration PV EPC BESS EPC Combined EPC Per MWp
1 MWp + 4 MWh €730,000 €674,000 €1,404,000 €1,404,000
2 MWp + 8 MWh €1,380,000 €1,084,000 €2,464,000 €1,232,000
3 MWp + 12 MWh €1,980,000 €1,643,000 €3,623,000 €1,208,000
5 MWp + 20 MWh €3,200,000 €2,253,000 €5,453,000 €1,091,000
10 MWp + 40 MWh €6,100,000 €4,392,000 €10,492,000 €1,049,000

5.2 All-In Investment (Including RTB License)

Configuration EPC Price RTB License All-In Investment Per MWp
1 MWp + 4 MWh €1,404,000 €350,000 €1,754,000 €1,754,000
2 MWp + 8 MWh €2,464,000 €700,000 €3,164,000 €1,582,000
5 MWp + 20 MWh €5,453,000 €1,750,000 €7,203,000 €1,441,000
10 MWp + 40 MWh €10,492,000 €3,500,000 €13,992,000 €1,399,000
All prices exclude VAT (19%). RTB = Ready-to-Build license at €350,000/MWp.

Custom configurations and multi-site portfolio pricing available on request.

6. EPC Packages

Standard EPC
€0.61–0.73/Wp
Target IRR: 8–10%
  • Site assessment & design
  • Tier-1 component procurement
  • Construction by certified specialists
  • Grid connection & commissioning
  • Performance warranties
  • O&M transition support

Ideal for: 1–5 MWp projects
Timeline: 4–8 months

Custom Solutions
Custom pricing
Target IRR: 8–13%
  • Tailored system design
  • Specialized equipment selection
  • Unique site accommodation
  • Flexible milestone planning
  • Extended warranty options
  • Portfolio pricing for multi-site

Ideal for: All sizes with special requirements
Timeline: Variable

7. Commercial Terms

7.1 Payment Schedule

Milestone Percentage Trigger
Advance Payment 25% Contract signing
Ready to Ship 50% Equipment ready for dispatch at factory
On-Site Delivery 20% Equipment delivered and verified on site
Final Acceptance 5% Pass Site Acceptance Test (SAT)

7.2 Delivery Timeline

PhaseDurationDescription
Manufacturing13 weeksEquipment production and factory testing
Shipping & Logistics7 weeksCIF delivery to Cyprus port, customs clearance
Installation4–6 weeksOn-site installation and commissioning per unit
Total24–26 weeksContract signing to commercial operation

7.3 Warranties & Guarantees

ItemCoverage
Manufacturer Warranty5 years (equipment defects & workmanship)
SOH Year 10≥79.6% minimum (at 1 cycle per day)
SOH Year 15≥73.6% minimum (at 1 cycle per day)
Advance Payment Guarantee100% bank guarantee on advance payment
Performance BondCorporate guarantee through delivery

7.4 O&M Services

Post-Commissioning O&M: €1,740 per MWh per year

8. Equipment & Technology Partners

8.1 Tier-1 Supply Chain

Linyang
Battery Systems

ME Series containers, EVE 314Ah LFP cells, integrated BMS/cooling/fire suppression

Kehua
PCS / Inverters

BCS1250K-C & BCS10000K-C-HUD, grid forming capable, ≥99% efficiency

Schneider
Switchgear & Protection

RM AirSeT 12-24kV, auxiliary transformers, protection relays

Huawei
PV Inverters

100-115kW string inverters, advanced MPPT, grid support functions

8.2 Additional BESS Partners

As an official Tier-1 BESS reseller, Lighthief also works with:

9. Why Cyprus for Solar Investment

3,300+
Annual Sun Hours
1,800+
kWh/m²/year Irradiation
12.5%
Corporate Tax Rate

9.1 The Curtailment Opportunity

Cyprus solar curtailment has increased from 0% (2021) to 45.8% (2025), making BESS integration essential for new projects. This creates a significant opportunity for storage-equipped solar parks to capture premium returns through energy arbitrage.

YearCurtailment %Investment Implication
20210%Full revenue capture
202313.4%BESS advantage begins
202545.8%BESS essential for ROI protection

9.2 Investment Returns

Scenario (5 MWp Example)InvestmentAnnual ProfitEquity ROI
Solar Only (Cash)€7,500,000€1,000,00013.3%
Solar + BESS (Cash)€9,250,000€1,260,00013.6%
Solar + BESS (70% Financed)€2,775,000 equity€560,00020.2%

10. Next Steps

10.1 How to Get Started

1
Submit EPC Request
Fill in the request form below or contact us directly. Share your project size, location, and timeline preferences.
2
Receive Proposal
Within 5 business days, receive a detailed EPC proposal with pricing, timeline, and financial projections tailored to your project.
3
Site Assessment
Our Cyprus-based team conducts a thorough site assessment and finalizes the technical design and commercial terms.
4
Contract & Build
Sign the EPC contract and we handle everything from procurement through commissioning and O&M transition.

10.2 Contact Information

Cyprus DirectorAlexander Papacosta
WhatsApp+357 99 164 158
Emailoffice@lighthief.com
Office+357 77 77 00 50
Websitewww.solarfarms.cy
Schedule Meetingcalendly.com/lighthiefcyprus

Request EPC Proposal

Complete the form below and our team will prepare a tailored EPC proposal within 5 business days.

We respond within 2 business days. Your information is treated as confidential.