Solar Parks #2205 + #2206 — Combined Package (2.817 MW)
Nicosia District, Cyprus
Connection terms pending
#2205 (0.5 MWp): Construction complete — grid connection terms pending · #2206 (2.317 MWp + BESS): Tier 1 licensed, permits in place · Land: FREEHOLD on both plots · Grid: formal EAC connection terms pending
2.817 MWp
PV capacity
#2205: 0.5 MWp built · #2206: 2.317 MWp ground-mounted RTB
6 MWh
BESS (4h)
LFP · 1.5 MW
~13–16%
Lev. equity IRR
indicative †
4.65 GWh
Annual production
1,650 kWh/kWp·yr
€327K
Solar rev Y1
2,324 MWh × €141/MWh
€283K
BESS rev Y1
1,450 MWh × €195/MWh
€610K
Gross Y1 revenue
before fees & tax
Revenue mechanics
50% curtailment (Cyprus 2027 baseline). BESS captures 72% → dispatches at DAM evening peak. RTE 86.32% AC–AC.
| Source | MWh/yr | €/MWh | Y1 Revenue |
| Solar — uncurtailed 50% |
2,324 |
140.88 |
€327K |
| BESS — curtailed × capture × RTE |
1,450 |
195.00 |
€283K |
| Total gross Y1 |
3,774 |
— |
€610K |
Wholesale reference (DAM)
| Price block | Measured | Model used |
| 24h average | 158 | — |
| Daytime 06:00–17:00 (solar sell) | 141 | 141 |
| Evening peak 17:00–21:00 (BESS discharge) | 183 | 195 |
| Apr 2026 observed peak | >340 | — |
Measured: 134 TSOC day-ahead days (1 Oct 2025 – 11 Feb 2026). Model uses €195/MWh discharge price (blended conservative; actual measured avg €183, Apr peak >€340).
Investment summary
| Component | EUR |
| RTB acquisition (SPV share purchase) | €1.85M |
| PV EPC — 2.817 MWp | €1.67M |
| BESS EPC — 1.5 MW / 6 MWh | €762K |
| Total (100% equity) | €4.28M |
⚠ EAC grid connection terms pending — priced separately (case-by-case).
Investment structure (100% equity)
| Item | Value | Notes |
| RTB acquisition | €1.85M | Excl. EAC grid connection terms |
| PV EPC | €1.67M | €0.72/Wp turnkey — #2206 only (#2205 already constructed) |
| BESS EPC (1.5 MW / 6 MWh) | €762K | €127k/MWh ex VAT (Tier-1 LFP OEM, Lighthief installed) |
| Total equity required | €4.28M | 100% equity — no debt |
| Y1 gross revenue | €610K | Solar + BESS |
| Aggregator fee (10%) | −€61K | Of gross revenue |
| Y1 OPEX | −€93K | O&M + land + insurance |
| Y1 EBITDA | €456K | EBITDA margin 75% |
| D&A (est., tax shield) | −€245K | PV+BESS 20yr · RTB 15yr SL |
| Cyprus CIT 15% on taxable income | −€32K | From 1 Jan 2026 |
| Y1 free cash flow | €424K | 9.9% cash-on-cash yield |
Y1 OPEX breakdown
| Cost line | €/yr |
| PV O&M | €42K |
| BESS O&M (LTSA basis) | €15K |
| Land lease | €0K |
| Insurance + admin + monitoring | €36K |
| Total OPEX Y1 | €93K |
Equity investment options
| Stake | Investment € | Y1 FCF € | Cash yield |
| 25% stake | €1,070K | €106K | 9.9% |
| 50% stake | €2,140K | €212K | 9.9% |
| 100% stake | €4,280K | €424K | 9.9% |
Revenue sensitivity
| Curtailment scenario | Y1 Gross Rev | Indic. IRR |
| Upside — 35% curtailment | €665K | ~19–23% |
| Base — 50% curtailment | €610K | ~13–16% |
| Downside — 65% curtailment | €512K | ~11–15% |
Project timeline
| Milestone | Status |
| CERA generation licence | Issued |
| Town planning & building permits | Issued |
| Environmental approvals | Issued |
| Land lease / site control | Executed |
| EAC grid connection | Prelim. filed — offer expected Q3 2026 |
| EPC contract (Lighthief) | Upon NDA |
| Financial close | Upon EAC offer (expected Q3 2026) |
| Target COD | #2205: target energisation Q3 2026 · #2206: target COD Q4 2026 |
Investment rationale
Why Cyprus BESS now?
Curtailment on the island grid is rising rapidly (50%+ at peak solar hours). BESS earns at €0 charge cost — storing otherwise-curtailed solar and dispatching at evening peak (€183–340/MWh). This structural arbitrage is locked in before DAM grid-charging legislation (expected 2027+) further compresses economics for late movers.
Key risks
Low Technology — Tier-1 LFP BESS, 7,000-cycle / 15yr warranty.
Low Permitting — CERA + planning already issued.
Med Grid connection — Grid connection awaiting DSO formal offer on both plots (#2205 already constructed)
Med DAM price — conservative TSOC sample used; April peaks >€340/MWh.
Low Regulatory — Cyprus CIT 15% fixed from Jan 2026.
Non-binding indicative summary. Figures based on Lighthief EPC pricing schedule (v4 Feb 2026), TSOC DAM sample (Oct 2025–Feb 2026), and project documentation on file. Not a prospectus or offer. Investors must conduct independent due diligence and obtain legal and tax advice. Full dataroom, Excel financial model, and EPC term sheet available under NDA. All figures ex VAT unless stated. Timeline subject to EAC and regulatory progress. Lighthief Cyprus Ltd (HE 477423).
To receive the full dataroom and Excel model:
Alexander Papacosta — Cyprus Director · +357 99 164 158 · office@lighthief.com
Lighthief Cyprus Ltd · solarfarms.cy · +357 77 77 00 50