Lighthief Cyprus
Hybrid Solar + BESS — Cyprus
INVESTOR TEASER — Page 1/2
PARK-RTB-VAN-2026
Confidential — May 2026

Agios Ioannis Malountas Solar Parks (10.4 MWp)

Agios Ioannis Malountas, Nicosia District, Cyprus
Connection terms pending
CERA production licences (extended to 31/12/2029) · Town planning permits issued · Building permits issued · Environmental approval (Dept of Environment) · Land leases valid to 2051 · EAC preliminary grid terms issued · ⚠ TSO confirmed no area grid capacity (Jan 2023); area substation upgrade in progress by EAC/TSO (est. completion Q4 2026)
10.4 MWp
PV capacity
Fixed-tilt monofacial PV
20 MWh
BESS (4h)
LFP · 5 MW
€10.43M
Total CAPEX
ex VAT
~13–15%
Lev. equity IRR
indicative †
17.16 GWh
Annual production
1,650 kWh/kWp·yr
€1,209K
Solar rev Y1
8,580 MWh × €141/MWh
€943K
BESS rev Y1
4,834 MWh × €195/MWh
€2,151K
Gross Y1 revenue
before fees & tax

Revenue mechanics

50% curtailment (Cyprus 2027 baseline). BESS captures 65% → dispatches at DAM evening peak. RTE 86.32% AC–AC.

SourceMWh/yr€/MWhY1 Revenue
Solar — uncurtailed 50% 8,580 140.88 €1,209K
BESS — curtailed × capture × RTE 4,834 195.00 €943K
Total gross Y1 13,414 €2,151K

DAM basis: 134 TSOC day-ahead days (1 Oct 2025 – 11 Feb 2026). BESS charges from curtailed solar at €0 cost. Grid arbitrage (buy/sell) not yet legal in Cyprus (Feb 2026). Spring/summer peaks observed >€340/MWh (Apr 2026); figures use conservative winter-biased sample.

Wholesale reference (DAM)

Price blockMeasuredModel used
24h average158
Daytime 06:00–17:00 (solar sell)141141
Evening peak 17:00–21:00 (BESS discharge)183195
Apr 2026 observed peak>340

Measured: 134 TSOC day-ahead days (1 Oct 2025 – 11 Feb 2026). Model uses €195/MWh discharge price (blended conservative; actual measured avg €183, Apr peak >€340).

Investment summary

ComponentEUR
RTB acquisition (SPV share purchase)€400K
PV EPC — 10.4 MWp€7.49M
BESS EPC — 5 MW / 20 MWh€2.54M
Total (100% equity)€10.43M

⚠ EAC grid connection terms pending — priced separately (case-by-case).

Lighthief Cyprus
Hybrid Solar + BESS — Cyprus
INVESTOR TEASER — Page 2/2
PARK-RTB-VAN-2026
Confidential — May 2026

Investment structure (100% equity)

ItemValueNotes
RTB acquisition€400KExcl. EAC grid connection terms
PV EPC€7.49M€0.72/Wp turnkey (Lighthief)
BESS EPC (5 MW / 20 MWh)€2.54M€127k/MWh ex VAT (Tier-1 LFP OEM, Lighthief installed)
Total equity required€10.43M100% equity — no debt
Y1 gross revenue€2,151KSolar + BESS
Aggregator fee (10%)−€215KOf gross revenue
Y1 OPEX−€303KO&M + land + insurance
Y1 EBITDA€1,634KEBITDA margin 76%
D&A (est., tax shield)−€528KPV+BESS 20yr · RTB 15yr SL
Cyprus CIT 15% on taxable income−€166KFrom 1 Jan 2026
Y1 free cash flow€1,468K14.1% cash-on-cash yield

Y1 OPEX breakdown

Cost line€/yr
PV O&M€156K
BESS O&M (LTSA basis)€49K
Land lease€30K
Insurance + admin + monitoring€67K
Total OPEX Y1€303K

Equity investment options

StakeInvestment €Y1 FCF €Cash yield
25% stake€2,607K€367K14.1%
50% stake€5,214K€734K14.1%
100% stake€10,428K€1,468K14.1%

100% equity structure — no bank debt. Cash yield = Y1 FCF (post-tax) × stake %. Full 25-year model available under NDA.

Revenue sensitivity

Curtailment scenarioY1 Gross RevIndic. IRR
Upside — 35% curtailment€2,455K~20–24%
Base — 50% curtailment€2,151K~13–15%
Downside — 65% curtailment€1,789K~11–15%

Revenue increases with higher curtailment because BESS dispatches at evening peak (€183/MWh avg) vs direct solar (€141/MWh avg) — provided BESS is sized to capture daily curtailed volume.

Project timeline

MilestoneStatus
CERA generation licenceIssued
Town planning & building permitsIssued
Environmental approvalsIssued
Land lease / site controlExecuted
EAC grid connectionPending area grid upgrade (TSO est. Q4 2026)
EPC contract (Lighthief)Upon NDA
Financial closeConditional on grid upgrade (ETA Q4 2026)
Target COD2027/2028

Investment rationale

Why Cyprus BESS now?
Curtailment on the island grid is rising rapidly (50%+ at peak solar hours). BESS earns at €0 charge cost — storing otherwise-curtailed solar and dispatching at evening peak (€183–340/MWh). This structural arbitrage is locked in before DAM grid-charging legislation (expected 2027+) further compresses economics for late movers.
Key risks
Low Technology — Tier-1 LFP BESS, 7,000-cycle / 15yr warranty.
Low Permitting — CERA + planning already issued.
High Grid connection — Preliminary DSO refs issued (400387217–400387472). TSO confirmed no area grid capacity (Jan 2023). EAC/TSO area substation upgrade in progress — est. completion Q4 2026. Final binding terms not yet issued.
Med DAM price — conservative TSOC sample used; April peaks >€340/MWh.
Low Regulatory — Cyprus CIT 15% fixed from Jan 2026.
Non-binding indicative summary. Figures based on Lighthief EPC pricing schedule (v4 Feb 2026), TSOC DAM sample (Oct 2025–Feb 2026), and project documentation on file. Not a prospectus or offer. Investors must conduct independent due diligence and obtain legal and tax advice. Full dataroom, Excel financial model, and EPC term sheet available under NDA. All figures ex VAT unless stated. Timeline subject to EAC and regulatory progress. Lighthief Cyprus Ltd (HE 477423).
To receive the full dataroom and Excel model:
Alexander Papacosta — Cyprus Director · +357 99 164 158 · office@lighthief.com
Lighthief Cyprus Ltd · solarfarms.cy · +357 77 77 00 50