Sia Solar Park with Battery Storage
Investor pack — indicative materials only; not an offer to sell securities.
Разрешения
CERA generation licence issued (Apr 2025) · Town planning permit issued (May 2025) · EIA approved · Land lease executed · EAC grid connection terms issued (ref 498000141 + Amendment 5, Jun 2025) · Substation sublease formalisation in progress
Сеть и сроки
EAC preliminary terms issued Feb 2023 (ref 498000141); 5% acceptance deposit paid Feb 2023; Amendment 5 issued Jun 2025. Grid infrastructure cost confirmed ~€84k ex VAT. Final binding terms pending substation building permit + sublease (FL4145)
Target COD Q3 2027 (subject to EAC grid connection finalisation)
Техническая сводка
Ориентир экономики
Только ориентир, не оферта. Смотрите тизер и своих консультантов.
| Статья | Ориентир (€) |
|---|---|
| Покупка RTB (запрос продавца) | €1,760,000 |
| EPC солнечной генерации | €2,304,000 |
| EPC BESS | €952,500 |
| Условия подключения | €83,842 |
| Итоговый ориентир | €5,100,342 |
| Валовая выручка энергии 1-го года (модель) | €661,057 |
| OPEX 1-го года (ориентир) | €102,627 |
BESS 2.5 MW / 7.5 MWh (3h) sized for E-W 10° curtailment profile (~45% base vs 50% south). PV yield from PVGIS E-W model (scripts/pvgis-park-yield.py, Jun 2026). Figures based on Lighthief EPC pricing and TSOC DAM sample (Oct 2025 – Feb 2026). Материалы ориентировочные и конфиденциальные. Проверено: 2026-05-09. Lighthief Cyprus Ltd (HE 477423) — solarfarms.cy